Beijing city in 2015 to do a good program of the division of labor projects
0000-00-00 00:00:00
One, to improve the living conditions of the masses
1 ease the housing difficulties of low-income families, the construction of affordable housing 105000 sets, 80000 sets of.
Finish time: before the end of 2015 11
The main responsibility units: the city housing and Urban Construction Committee, the city development and Reform Commission, the City Planning Commission, City Land Bureau, district county government
Project Leader: the city Housing Urban and Rural Construction Committee Xu Jianyun, city development and Reform Commission Lu Yan, City Planning Commission Huang Yan, City Land Bureau Wei Chenglin, district county government district magistrate
. improvement of the old residential environment, continue to seismic reinforcement, energy-saving insulation, public area comprehensive improvement, including water, electricity, gas, heat, communication and the conditions of the old facilities such as lifts, etc. comprehensive renovation and transformation of a simple floor, a total of 115 million square meters.
Finish time: before the end of 2015 11
Main responsibility units: city major projects, the county government
Project is responsible for the project: the city's major projects to do Xu Jianyun, district county government district
Co organizer: City Housing Urban and Rural Construction Committee, municipal committee, municipal development and Reform Commission, the Municipal Finance Bureau, the Municipal Planning Commission, the Municipal Bureau of quality supervision
Two, convenient public travel
3. The improvement of citizens in the city center and key metro transportation efficiency, rail transportation line 14 middle, Changping line phase II a total of 25 km line was opened to traffic. By the end of 2015 railway operating mileage reached 550 km.
Finish time: before the end of 2015 12
The main responsibility of the unit: the city's major projects, the Municipal Transportation Commission, the government of Dongcheng District, Chaoyang District government, Fengtai District government, Changping District government
Project is responsible for the project: the city's major projects to do Xu Jianyun, Municipal Transportation Committee Zhou Zhengyu, Dongcheng District government Zhang Jiaming, Chaoyang District government, government, Fengtai District government, government, Changping District government Zhang Yanyou
4. To further improve the rail transit facilities, line 13 and Batong line safety door and put to use, transformation of the 1st line, 2nd line, on the 13th line, Batongxian station toilets, improve station sign system.
Finish time: before the end of 2015 12
Main responsibility unit: Municipal Transportation Commission
Project Leader: City Traffic Commission Zhou Zhengyu
5. To encourage residential parking management autonomy and construction of the six districts of the city completed 12 parking management demonstration area; parking management behavior norms, consolidation of 100 parking order management model Street results, investigate and punish the illegal parking behavior.
Finish time: before the end of 2015 11
Main responsibility: Dongcheng District government, Xicheng District government, Chaoyang District government, Haidian District government, Fengtai District government, Shijingshan District government, City Transportation Commission, the municipal social office, city housing and Urban Construction Commission, the Municipal Public Security Bureau, the Municipal Urban Management Law Enforcement Bureau
Person in charge of the project: Dongcheng District Government Zhang Jiaming, Xicheng District Government Wang Shaofeng, Chaoyang District government Wu Guiying, Haidian District government sun Wenkai, Fengtai District government Ji Yan, Shijingshan District government Xia Lin, City Traffic Commission Zhou Zhengyu, city social do song Guilun, city housing and Urban Construction Committee Xu Jianyun, City Public Security Bureau Wang Xiao Hong, city urban management and Law Enforcement Bureau]
6. To improve passenger waiting environment, transformation of the 100 bus stop, Station Pavilion, fence and other infrastructure; adjustment and optimization of public traffic line network, open, adjust the bus line 40; combined with the rail traffic to the opening of the new line, improve the bus station and subway stations lead identification.
Finish time: before the end of 2015 11
Main responsibility unit: Municipal Transportation Commission
Project Leader: City Traffic Commission Zhou Zhengyu
Co organizer: Municipal Public Security Bureau, the Municipal Commission, the Municipal Gardens Bureau, city urban management and Law Enforcement Bureau, Dongcheng District government, government of Xicheng District, Chaoyang District government, Haidian District government, Fengtai District government, Shijingshan District Government
7 complete 100 million square meters of urban road maintenance tube, in perfect sync slow system of road 80 km, protect the sidewalk, bicycle lanes of continuity; the completion of 30 dredging projects.
Finish time: before the end of 2015 11
Main responsibility unit: Municipal Transportation Commission
Project Leader: City Traffic Commission Zhou Zhengyu
Co organizer: Municipal Public Security Bureau, City Garden Greening Bureau
8 to expand the scale of public bicycle construction, increase the service site, new (build) public bicycle 7000, to facilitate the public green travel.
Finish time: before the end of 2015 11
The main responsible units: city traffic appoint, Dongcheng District government, the government of Xicheng District, Chaoyang District government, Haidian District government, Fengtai District government, Shijingshan District government, Tongzhou District government, Fangshan District government, Shunyi District Government
Person in charge of the project: city traffic Wei Zhou Zhengyu, Dongcheng District Government Zhang Jiaming, Xicheng District Government Wang Shaofeng, Chaoyang District government Wu Guiying, Haidian District government sun Wenkai, Fengtai District government Ji Yan, Shijingshan District government Xia Lin, Tongzhou District government Yue Peng, Fangshan District government had praise wing, Shunyi District Government Lu Yingchuan
9 complete Xicheng District Music Factory Road, Fengtai District road and other road, road, and other road construction, improve the surrounding people at night travel conditions.
Finish time: before the end of 2015 11
Main responsibility unit: Municipal Committee
Project Leader: Municipal Committee Sun Xinjun
Co organizer: Municipal Public Security Bureau, the City Planning Commission, City Transportation Commission, the Municipal Gardens Bureau, Dongcheng District government, government of Xicheng District, Chaoyang District government, Haidian District government, Fengtai District government, Shijingshan District Government